Erosion & Sediment Control
Highway 63 Wandering River 2014
 
Project Description:  Construction of highway 63 at Wandering River
Owner: Alberta Transportation
Consultant: EBA Engineers
Prime Contractor: Thompson Bros. (Construction) LP
 
Scope of work:  Supply and installation of erosion and sediment control measures including:
  • Gabion matresses/geogrid
  • Erosion control blankets(RECP)
  • Turf reinforcement mats(TRM)
  • Synthetic permeable ditch barriers (georidge)
  • Silt fence
  • Hydroseeding
  • Tree planting

 

 
North Gilt Edge Road Wainwright 2014
 
Project Description:  Reconstruction and Grading of Range Road 55 and 53 from Highway 614 North to Battle River
Owner: MD of Wainwright
General Contractor: CEE GEE Southern Inc.
Sub Contractor: Erscon Canada Inc.
 
Scope of WorkSupply and installation of Erosion control measures including:

 

  • Silt fence
  • Synthetic Permeable Ditch Barriers (georidge)
  • HECP(Hydraulic Erosion Control Products)
  • Hydroseeding
  • Broadcast Seeding

 

 

 
 
 
AT 11161 – Town of Athabasca
Contract Date: May 2013
Owner: Alberta Transportation
General Contractor: Carmacks Enterprises Ltd.
Sub Contractor: Erscon Canada Inc.
Project Details:
  1. Supply and installation of Gabion Baskets
  2. Supply and installation of Gabion Mattresses
  3. Supply and installation of Geotextile
  4. Supply and installation of Erosion Control Mat
  5. Supply and installation of Erosion Control Barrier
  6. Supply and installation of Harvesting
  7. Supply and installation of Brush Layering
  8. Supply and installation of Pole Planting
  9. Supply and installation of Vegetative Plantings
  10. Supply and installation of Live Staking
  11. Supply and installation of Hydroseeding
  12. Supply and installation of Topsoil Placement
 
Alberta Transportation 8053/10 – Drayton Valley, AB
Contract Date: April 2011
Owner: Alberta Transportation
Consultant: Associated Engineering Alberta Ltd.
Prime Contractor: Pidherney’s
Project Details:        
1) Supply and installation of Erosion Control Covering (Type B)
2) Supply and installation of Erosion Control Covering (Type C)
3) Supply and installation Synthetic Permeable Ditch Barrier
  
 
Petro Canada Fort Hills – Fort McMurray, AB
Contract Date: August 2010
Owner: Suncor Energy
Consultant: Paragon Soils Ltd.
Prime Contractor: Erscon Canada Inc.
Project Details:        
Supply and installation of a bonded fibre matrix hydromulch (3100 kg/ha) with a native seed blend (30 kg/ha) installed onto sand slopes for stabilization.
 
 
Alberta Transportation 7964/09 - Highway 40, Concrete Pile Wall
Contract Date: June 2010
Owner: Alberta Transportation
Consultant: Thurber Engineering Ltd.
Prime Contractor: ConCreate USL Ltd.
Project Details:        
Supply and installation of a 50 mm depth EcoBlanket™, placed onto the highway side slopes for erosion protection and stabilization.
 
 
Devon Canada – Lease Road Access
Contract Date: July 2010
Owner: Devon Canada
Consultant: Townsend Environmental Consulting
Prime Contractor: Erscon Canada Inc.
Project Details:        
Supply and installation of a bonded fibre matrix hydromulch (2800 kg/ha) with a native seed blend (100kg/ha); installed on the new access road ditches and side slopes.
 
 
Kearl Lake Oil Sands Project R.W.I.
Contract Date: August 2009
Owner: Imperial Oil Resources Ventures Ltd.
Consultant: AMEC
Prime Contractor: K2 Mining
Project Details:        
Supply and installation of a 25 mm depth EcoBlanket™, placed onto the access road side slopes and top soil pile for erosion protection, stabilization and revegetation.
 
 
Alberta Transportation 7793/08 – McGregor Reservoir – West Valley Slope Revegetation
Contract Date: September 2008
Owner: Alberta Transportation
Consultant: Alberta Transportation
Prime Contractor: Top Notch Construction Ltd.
Project Details:        
1) Supply & installation of LockDown™ netting.
2) Supply and installation of 300 mm diameter FilterSoxx™
3) Supply and installation of a 50 mm depth EcoBlanket™
 
 
Wolf Willow Slope Repair & Revegetation – Edmonton, AB
Contract Date: July 2008
Owner: Centennial Valley Properties
Consultant: Thurber Engineering Ltd.
Prime Contractor: Erscon Canada Inc.               
Subcontractor: Wilco Contractors NW Inc.
Project Details:        
Excavating, cleanup, reshaping, soft armouring and revegetation establishment on three steep slopes within the North Saskatchewan River Valley in West Edmonton.   
1) Supply & installation of LockDown™ netting.
2) Supply and installation of 200 mm diameter FilterSoxx™
3) Supply and installation of a 75 mm depth EcoBlanket™
4) Supply and installation of a Turf Reinforcement Mat (TRM)
5) Supply and planting of native plugs and seed blend.
6) Provide two year warranty and maintenance.
 
 
Alberta Transportation 7362/07 – Hwy 986, Diashowa East Access
Contract Date: July 2007
Owner: Alberta Transportation
Consultant: Thurber Engineering Ltd.
Prime Contractor: Core Energy Solutions
Project Details:
1)    Supply and installation of 300 mm diameter ChannelSoxx™
2)    Supply and installation of Permanent Rolled Erosion Control Covering (TRM)
 
 
Shell Scotford Pump House River Bank Stabilization
Contract Date: June 2006
Owner: Shell Canada Ltd.
Consultant: Colt Engineering
Prime Contractor: Voice Construction Ltd.  
Project Details:        
1) Supply & installation of LockDown™ Netting.
2) Supply and installation of a 50 mm depth EcoBlanket™